• General Sullivan recommendation for a canal earlier. (1779)

  • 1826 Surveys made from Seneca Lake to Chemung River

  • 1830 contracts let for $290,263 work began to be completed in October

  • 1831 Fifteen miles of canal completed

  • Dam in Chemung river completed, 645 x 7 Ft